Project Description
Project Manager
Laura Harrell
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 03-Jan-2024 12-Aug-2025
100%
PE - Preliminary 03-Jan-2024 14-May-2024
100%
PE - Design 15-May-2024 12-Aug-2025
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Dec-2024 18-Jun-2025
100%
Right of Way 05-Dec-2024 18-Jun-2025
100%
ROW - Land Acquisition 05-Dec-2024 18-Jun-2025
100%
ROW - Utility Relocation 05-Dec-2024 18-Jun-2025
100%
Construction 08-Sep-2025 07-Jan-2026
100%
CA - Pre-Ad 03-Jun-2025 03-Jun-2025
100%
CA - Advertisement 04-Jun-2025 04-Jun-2025
100%
CA - Bid Date 05-Jun-2025 05-Jun-2025
100%
CA - Construction Award 08-Sep-2025 08-Sep-2025
100%
CA - CEI 09-Sep-2025 09-Sep-2025
100%
CA - Construction 09-Sep-2025 06-Jan-2026
100%
CA - Construction Closeout 07-Jan-2026 07-Jan-2026
100%
Project Closeout 08-Jan-2026 08-Jan-2026
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
SECRA - Wickham Ave Gravity Sewer Relocation Design ATCS, P.L.C 15-May-2024 12-Feb-2025 $189,555.25 $180,051.85
CA - Construction TIDEWATER UTILITY CONSTRUCTION 24-Oct-2025 01-May-2026 $2,485,592.14 $1,538,951.85

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.