Project Description
Location: This project replaces the sanitary sewer force main starting at Pump Station 043 (117 Pocahontas Drive) and terminating with a a connection to an existing manhole (WCMH002861) at the intersection of Warwick & Denbigh Blvd
Project Manager
Landon Kee
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 02-Nov-2018 04-May-2026
99%
PE - Preliminary 02-Nov-2018 02-Nov-2018
100%
PE - Design 25-Jan-2022 04-May-2026
98%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 10-May-2026 17-Jul-2027
CA - Pre-Ad 10-May-2026 08-Jun-2026
CA - Advertisement 09-Jun-2026 08-Jul-2026
CA - Bid Date 09-Jul-2026 09-Jul-2026
CA - Construction Award 10-Jul-2026 16-Jul-2026
CA - CEI 17-Jul-2026 30-Jul-2026
CA - Construction 17-Jul-2026 16-Jul-2027
CA - Construction Closeout 17-Jul-2027 17-Jul-2027
Project Closeout 18-Jul-2027 18-Jul-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.