Project Description
Location: 17 GWYNN CIR
Project Manager
Laura Harrell
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 08-Apr-2024 25-Oct-2026
82%
PE - Preliminary 08-Apr-2024 07-Feb-2025
100%
PE - Design 22-Aug-2025 22-Oct-2026
61%
PE - Environmental 23-Oct-2026 23-Oct-2026
PE - Scoping 24-Oct-2026 24-Oct-2026
PE - Public Involvement 25-Oct-2026 25-Oct-2026
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 25-Oct-2026 28-Oct-2027
CA - Pre-Ad 25-Oct-2026 25-Oct-2026
CA - Advertisement 26-Oct-2026 26-Oct-2026
CA - Bid Date 27-Oct-2026 27-Oct-2026
CA - Construction Award 28-Oct-2026 28-Oct-2026
CA - CEI 29-Oct-2026 29-Oct-2026
CA - Construction 29-Oct-2026 27-Oct-2027
CA - Construction Closeout 28-Oct-2027 28-Oct-2027
Project Closeout 29-Oct-2027 29-Oct-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Consultant for PS038 Rebuild PER Dewberry Engineers Inc. 08-Apr-2024 09-Aug-2024 $74,470.00 $74,470.00
PE - Design Dewberry Engineers Inc. 19-Aug-2025 19-Apr-2027 $484,988.00 $131,925.50

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.