Activity Start Finish % Complete
PE/Design 01-Jan-2026 30-Jun-2026
92%
PE - Preliminary 01-Jan-2026 01-Mar-2026
100%
PE - Design 02-Mar-2026 29-Jun-2026
89%
PE - Environmental 30-Jun-2026 30-Jun-2026
PE - Scoping 02-Mar-2026 02-Mar-2026
100%
PE - Public Involvement 30-Jun-2026 30-Jun-2026
Right of Way 30-Jun-2026 30-Jun-2026
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 30-Jun-2026 30-Jun-2026
Construction 01-Jul-2026 18-Jan-2027
CA - Pre-Ad 01-Jul-2026 30-Jul-2026
CA - Advertisement 31-Jul-2026 29-Aug-2026
CA - Bid Date 30-Aug-2026 30-Aug-2026
CA - Construction Award 31-Aug-2026 20-Sep-2026
CA - CEI 21-Sep-2026 21-Sep-2026
CA - Construction 21-Sep-2026 19-Dec-2026
CA - Construction Closeout 20-Dec-2026 18-Jan-2027
Project Closeout 19-Jan-2027 17-Feb-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.