Project Description
Location: 57 Madison Ln N
Project Manager
Wendy Royston
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 06-Feb-2026 05-May-2028
19%
PE - Preliminary 06-Feb-2026 06-Jan-2028
22%
PE - Design 07-Jan-2028 05-Apr-2028
PE - Environmental 06-Apr-2028 06-Apr-2028
PE - Scoping 07-Jan-2028 07-Jan-2028
PE - Public Involvement 06-Apr-2028 05-May-2028
Right of Way 06-Apr-2028 06-Apr-2028
ROW - Land Acquisition 06-Apr-2028 06-Apr-2028
ROW - Utility Relocation 06-Apr-2028 06-Apr-2028
Construction 07-Apr-2028 04-May-2029
CA - Pre-Ad 07-Apr-2028 03-Oct-2028
CA - Advertisement 04-Oct-2028 02-Nov-2028
CA - Bid Date 03-Nov-2028 03-Nov-2028
CA - Construction Award 04-Nov-2028 04-Nov-2028
CA - CEI 05-Nov-2028 05-Nov-2028
CA - Construction 05-Nov-2028 03-May-2029
CA - Construction Closeout 04-May-2029 04-May-2029
Project Closeout 05-May-2029 05-May-2029

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.