Project Description
Resurfacing pavement and associated concrete repairs.
Project Manager
Jennifer Butler
757-926-1582
butlerja@nnva.gov
Inspector
Ryan Reynolds
757-879-5679
reynoldsra@nnva.gov

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2023 27-Oct-2023
100%
PE - Design 01-Jul-2023 27-Oct-2023
100%
Construction 28-Oct-2023 10-Feb-2025
100%
CA - Advertisement 02-Jan-1900 03-Jan-1900
100%
CA - Construction Award 28-Oct-2023 26-Jan-2024
100%
CA - CEI 27-Jan-2024 10-Jan-2025
100%
CA - Construction 27-Jan-2024 10-Jan-2025
100%
CA - Construction Closeout 11-Jan-2025 10-Feb-2025
100%
Project Closeout 11-Feb-2025 11-Feb-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
2024 ANNUAL CITYWIDE RESURFACING AND CONCRETE REPAIR - WEST BRANSCOME, INC 29-Jan-2024 30-Jun-2024 $4,511,365.92 $4,241,344.54

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.