Project Description
Resurfacing pavement and associated concrete repairs throughout the City.
Project Manager
Jennifer Butler
757-926-1582
butlerja@nnva.gov
Inspector
Ryan Reynolds
757-879-5679
reynoldsra@nnva.gov

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2023 27-Oct-2023
100%
PE - Design 01-Jul-2023 27-Oct-2023
100%
Construction 28-Oct-2023 30-Dec-2024
100%
CA - Construction Award 28-Oct-2023 15-Jan-2024
100%
CA - CEI 16-Jan-2024 30-Sep-2024
100%
CA - Construction 16-Jan-2024 30-Sep-2024
100%
CA - Construction Closeout 01-Oct-2024 30-Dec-2024
100%
Project Closeout 31-Dec-2024 31-Dec-2024
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
2024 ANNUAL CITYWIDE RESURFACING AND CONCRETE REPAIR - EAST BASIC CONSTRUCTION CO.,L.L.C 11-Nov-2023 30-Jun-2024 $4,186,044.23 $3,803,735.13

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.