Project Description
Location: 907 Colleen DR
Project Manager
Laura Harrell
757-926-8449
roystonwc@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 10-Oct-2023 03-Jan-2027
90%
PE - Preliminary 10-Oct-2023 25-Oct-2024
100%
PE - Design 17-Nov-2025 03-Jan-2027
72%
PE - Environmental 26-Oct-2024 22-Feb-2025
100%
PE - Public Involvement 30-Dec-2023 27-Apr-2024
100%
Right of Way 30-Dec-2023 01-Dec-2025
100%
ROW - Land Acquisition 30-Dec-2023 01-Dec-2025
100%
ROW - Utility Relocation 30-Dec-2023 26-Jun-2024
100%
Construction 04-Jan-2027 19-Aug-2028
CA - Pre-Ad 04-Jan-2027 04-Jan-2027
CA - Advertisement 05-Jan-2027 03-Feb-2027
CA - Bid Date 04-Feb-2027 04-Feb-2027
CA - Construction Award 05-Feb-2027 05-Feb-2027
CA - CEI 06-Feb-2027 06-Feb-2027
CA - Construction 06-Feb-2027 18-Aug-2028
CA - Construction Closeout 19-Aug-2028 19-Aug-2028
Project Closeout 20-Aug-2028 20-Aug-2028
PE - Scoping 30-Dec-2023 27-Apr-2024
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
PER Services BURGESS & NIPLE, INC 10-Oct-2023 18-Feb-2024 $191,112.08 $173,433.92
ENGINEERING SERVICES - DESIGN - PS 056 REPLACEMENT BURGESS & NIPLE, INC 21-Feb-2025 01-Apr-2026 $534,915.00 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.