Project Description
Replacing force main constructed in 1964 in environmentally sensitive area.Location: Pump station is located behind 238 St Ives Cir. Existing force main extends from pump station down Fincastle Drive to the PS021 force main behind Chatsworth Drive. Proposed force main will follow Newmarket Creek to Chatsworth Drive.
Project Manager
Wendy Royston
757-926-8449
roystonwc@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 01-Sep-2023 13-Sep-2025
100%
PE - Preliminary 01-Sep-2023 07-Feb-2024
100%
PE - Design 15-Dec-2023 14-Aug-2025
100%
PE - Environmental 28-Feb-2025 14-Aug-2025
100%
PE - Public Involvement 15-Aug-2025 13-Sep-2025
100%
Right of Way 15-Aug-2025 12-Dec-2025
100%
ROW - Land Acquisition 15-Aug-2025 12-Dec-2025
100%
ROW - Utility Relocation 15-Aug-2025 12-Dec-2025
100%
Construction 13-Dec-2025 23-Dec-2027
20%
Hold for Funding 13-Dec-2025 08-Oct-2026
50%
CA - Advertisement 08-Nov-2026 07-Dec-2026
CA - Bid Date 08-Dec-2026 08-Dec-2026
CA - Construction Award 09-Dec-2026 22-Dec-2026
CA - CEI 23-Dec-2026 23-Dec-2026
CA - Construction 23-Dec-2026 22-Dec-2027
CA - Construction Closeout 23-Dec-2027 23-Dec-2027
Project Closeout 24-Dec-2027 24-Dec-2027
PE - Scoping 09-Sep-2023 07-Nov-2023
100%
CA - Pre-Ad 09-Oct-2026 07-Nov-2026

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
PS059 FORCE MAIN REPLACEMENT DESIGN ATCS, P.L.C 15-Dec-2023 15-Mar-2025 $123,281.94 $117,825.16

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.