Project Description
Long term program to analyze existing and historical data to prioritize rehabilitation projects for the sanitary sewer system.
Project Manager
Wendy Royston
757-926-8449
roystonwc@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE - Preliminary 09-Nov-2023 17-Dec-2027
63%
PE - Design 18-Dec-2027 16-Dec-2028
Construction 17-Dec-2028 06-Oct-2033
CA - Pre-Ad 17-Dec-2028 17-Dec-2028
CA - Advertisement 18-Dec-2028 18-Dec-2028
CA - Bid Date 19-Dec-2028 19-Dec-2028
CA - Construction Award 20-Dec-2028 20-Dec-2028
CA - CEI 21-Dec-2028 21-Dec-2028
CA - Construction 21-Dec-2028 05-Oct-2033
CA - Construction Closeout 06-Oct-2033 06-Oct-2033
Project Closeout 07-Oct-2033 07-Oct-2033

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.