Project Description
SCADA system needs to be replaced in 2028. Currently evaluating the City's data needs and available SCADA systems to prepare for the upgrade.
Project Manager
Wendy Royston
757-926-8449
roystonwc@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 01-Jun-2023 25-Jan-2028
61%
PE - Preliminary 01-Jun-2023 24-Feb-2026
100%
PE - Design 25-Feb-2026 25-Jan-2028
6%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
Construction 26-Jan-2028 27-Jun-2028
CA - Pre-Ad 26-Jan-2028 26-Jan-2028
CA - Advertisement 27-Jan-2028 25-Feb-2028
CA - Bid Date 26-Feb-2028 26-Feb-2028
CA - Construction Award 27-Feb-2028 27-Feb-2028
CA - CEI 28-Feb-2028 28-Feb-2028
CA - Construction 28-Feb-2028 26-Jun-2028
CA - Construction Closeout 27-Jun-2028 27-Jun-2028
Project Closeout 28-Jun-2028 28-Jun-2028
PE - Scoping 01-Dec-2023 30-Dec-2023
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.