Project Description
Project will repair and rehabilitate sewer that has washed out and stabilized stream banks to protect sewer. Location: 13236 Jefferson Ave and section of creek behind the pump station.
Project Manager
Wendy Royston
757-926-8449
roystonwc@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 06-Jun-2025 02-Dec-2027
33%
PE - Preliminary 06-Jun-2025 05-Jun-2027
42%
PE - Design 06-Jun-2027 02-Dec-2027
PE - Environmental 04-Oct-2025 31-Jan-2026
100%
PE - Public Involvement 09-Sep-2025 06-Jan-2026
100%
Right of Way 01-Feb-2026 31-May-2026
57%
ROW - Land Acquisition 01-Feb-2026 31-May-2026
57%
ROW - Utility Relocation 01-Feb-2026 01-Feb-2026
100%
Construction 03-Dec-2027 08-Dec-2027
CA - Pre-Ad 03-Dec-2027 03-Dec-2027
CA - Advertisement 04-Dec-2027 04-Dec-2027
CA - Bid Date 05-Dec-2027 05-Dec-2027
CA - Construction Award 06-Dec-2027 06-Dec-2027
CA - CEI 07-Dec-2027 07-Dec-2027
CA - Construction 07-Dec-2027 07-Dec-2027
CA - Construction Closeout 08-Dec-2027 08-Dec-2027
Project Closeout 09-Dec-2027 09-Dec-2027
PE - Scoping 09-Sep-2025 08-Oct-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.