Project Description
Project Manager
Lisa Frankenberger
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Feb-2024 22-Sep-2025
100%
PE - Preliminary 01-Feb-2024 10-May-2024
100%
PE - Design 11-May-2024 22-Sep-2025
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 23-Sep-2025 16-Nov-2025
100%
CA - Pre-Ad 23-Sep-2025 23-Sep-2025
100%
CA - Advertisement 24-Sep-2025 17-Oct-2025
100%
CA - Bid Date 17-Oct-2025 17-Oct-2025
100%
CA - Construction Award 18-Oct-2025 14-Nov-2025
100%
CA - CEI 15-Nov-2025 15-Nov-2025
100%
CA - Construction 15-Nov-2025 15-Nov-2025
100%
CA - Construction Closeout 16-Nov-2025 16-Nov-2025
100%
Project Closeout 17-Nov-2025 17-Nov-2025
100%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
School Speed Limit and Warning Signs BRYANT-RITTER HEWITT ELECTRIC CORP 05-Jan-2026 31-Dec-2026 $259,971.00 $78,735.14

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.