Project Description
The project scope includes the demolition and complete replacement of the timber pier and substructure including the T section at the end. The scope of work does not include the timber walkway, but does include installation of timber piles and "No Wake" signage adjacent to the pier.
Project Manager
Carolyn Bowman
757.926.3667
bowmancd@nnva.gov
Inspector
Jeff Everton

How does this project serve Newport News’ citizens?
The new pier will replace the existing, structurally deficient, pier.

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe
  • Respects its Uniqueness
  • Balances Good Places & New Spaces

Schedule

Activity Start Finish % Complete
PE/Design 13-Jun-2022 05-Aug-2024
100%
PE - Preliminary 13-Jun-2022 27-Aug-2023
100%
PE - Design 28-Aug-2023 05-Aug-2024
100%
PE - Environmental 28-Aug-2023 28-Jun-2024
100%
Construction 06-Aug-2024 10-Jun-2025
100%
CA - Pre-Ad 06-Aug-2024 11-Aug-2024
100%
CA - Advertisement 12-Aug-2024 09-Sep-2024
100%
CA - Bid Date 10-Sep-2024 10-Sep-2024
100%
CA - Construction Award 11-Sep-2024 29-Jan-2025
100%
CA - CEI 30-Jan-2025 19-May-2025
100%
CA - Construction 30-Jan-2025 19-May-2025
100%
CA - Construction Closeout 20-May-2025 10-Jun-2025
100%
Project Closeout 11-Jun-2025 09-Aug-2025
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Professional Services for Denbigh Fishing Pier Replacement MOFFATT AND NICHOL 28-Aug-2023 01-Nov-2025 $102,175.00 $95,903.36
Denbigh Fishing Pier Replacement CROFTON CONSTRUCTION SERVICES, INC 30-Jan-2025 28-Jun-2025 $406,677.00 $394,140.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.