Schedule
| Activity |
Start |
Finish |
% Complete |
| PE/Design |
18-Nov-2024 |
18-Mar-2026 |
|
| PE - Preliminary |
18-Nov-2024 |
15-Jun-2025 |
|
| PE - Design |
16-Jun-2025 |
18-Mar-2026 |
|
| Construction |
19-Mar-2026 |
20-Apr-2027 |
|
| CA - Pre-Ad |
19-Mar-2026 |
08-Apr-2026 |
|
| CA - Advertisement |
09-Apr-2026 |
06-May-2026 |
|
| CA - Bid Date |
13-May-2026 |
13-May-2026 |
|
| CA - Construction Award |
14-May-2026 |
24-Jun-2026 |
|
| CA - CEI |
25-Jun-2026 |
19-Feb-2027 |
|
| CA - Construction |
25-Jun-2026 |
19-Feb-2027 |
|
| CA - Construction Closeout |
20-Feb-2027 |
20-Apr-2027 |
|
| Project Closeout |
21-Apr-2027 |
19-Jun-2027 |
|
Contracts
| Contract Name |
Contractor/Consultant |
Start |
Finish |
Contract Amount |
Paid To Date |
The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.