Project Description
Repairs to the expansion joint as well as repairs from latest NBIS Inspection Report
Project Manager
Carolyn Bowman
Inspector

How does this project serve Newport News’ citizens?
It will repair the existing expansion joint.

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 18-Nov-2024 18-Mar-2026
92%
PE - Preliminary 18-Nov-2024 15-Jun-2025
100%
PE - Design 16-Jun-2025 18-Mar-2026
87%
Construction 19-Mar-2026 20-Apr-2027
CA - Pre-Ad 19-Mar-2026 08-Apr-2026
CA - Advertisement 09-Apr-2026 06-May-2026
CA - Bid Date 13-May-2026 13-May-2026
CA - Construction Award 14-May-2026 24-Jun-2026
CA - CEI 25-Jun-2026 19-Feb-2027
CA - Construction 25-Jun-2026 19-Feb-2027
CA - Construction Closeout 20-Feb-2027 20-Apr-2027
Project Closeout 21-Apr-2027 19-Jun-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.