The project involves the design of a new force main to replace the existing force main from pump station PS021. The PS021 force main requires relocation from its current location behind the residences along Chatsworth Drive to the roadway from the pump station to a point near 777 Chatsworth Drive where the relocated force main can connect to the HRSD Force Main. Due to the location of the force main in an easement behind residential properties, significant public involvement will be necessary. The force main is located in an environmentally sensitive area that would be adversely impacted should a failure occur. The force main is approaching the end of its useful life and is currently located in a difficult location to maintain or repair. Location: Existing force main runs from pump station at 260 Anne Dr. through backyards along Chatsworth Drive. New force main will extend from pump station at 260 Anne Dr. down Anne Drive to Chatsworth, to Newmarket Creek to the City of Hampton.
Project Manager
Wendy Royston
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Sep-2023 13-Sep-2025
100%
PE - Preliminary 01-Sep-2023 07-Feb-2024
100%
PE - Design 15-Dec-2023 14-Aug-2025
100%
PE - Environmental 28-Feb-2025 14-Aug-2025
100%
PE - Public Involvement 15-Aug-2025 13-Sep-2025
100%
Right of Way 15-Aug-2025 10-Feb-2026
100%
ROW - Land Acquisition 15-Aug-2025 10-Feb-2026
100%
ROW - Utility Relocation 15-Aug-2025 12-Dec-2025
100%
Construction 02-Mar-2026 11-Mar-2028
25%
CA - Pre-Ad 27-Dec-2026 25-Jan-2027
CA - Advertisement 26-Jan-2027 24-Feb-2027
CA - Bid Date 25-Feb-2027 25-Feb-2027
CA - Construction Award 26-Feb-2027 11-Mar-2027
CA - CEI 12-Mar-2027 12-Mar-2027
CA - Construction 12-Mar-2027 10-Mar-2028
CA - Construction Closeout 11-Mar-2028 11-Mar-2028
Project Closeout 12-Mar-2028 12-Mar-2028
PE - Scoping 09-Sep-2023 07-Nov-2023
100%
Hold for Funding 02-Mar-2026 26-Dec-2026
64%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
PS021 FORCE MAIN REPLACEMENT - DESIGN SERVICES ATCS, P.L.C 15-Nov-2023 15-Mar-2025 $298,637.74 $298,637.74

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.