Project Description
Wet well and equipment within wet well at Pump Station 065 have deteriorated significantly until it is no longer safe for personnel to enter. The first phase of this project will include an analysis of the structure and recommendations, including bid documents, for repairs to the wet well. The second phase will repair the wet well, replace the ventilation system, and make cosmetic repairs to the exterior of the structure. Location: 12148 Jefferson Avenue
Project Manager
Wendy Royston
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 05-May-2023 17-Jan-2025
100%
PE - Preliminary 05-May-2023 14-May-2023
100%
PE - Design 05-May-2023 31-Oct-2023
100%
PE - Environmental 16-Oct-2024 16-Oct-2024
100%
PE - Public Involvement 17-Jan-2025 17-Jan-2025
100%
Construction 01-Apr-2024 30-Aug-2025
100%
CA - Pre-Ad 01-Apr-2024 30-Apr-2024
100%
CA - Advertisement 15-May-2024 29-May-2024
100%
CA - Bid Date 30-May-2024 30-May-2024
100%
CA - Construction Award 31-May-2024 13-Jun-2024
100%
CA - CEI 11-Jul-2024 11-Jun-2025
100%
CA - Construction 14-Jan-2025 31-Jul-2025
100%
CA - Construction Closeout 01-Aug-2025 30-Aug-2025
100%
Project Closeout 31-Aug-2025 04-Sep-2025
100%
PE - Scoping 16-Oct-2024 16-Oct-2024
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Pump Station 065: Wet Well Structural Analysis and Bid Documents MCPHERSON DESIGN GROUP, PC 15-Nov-2022 15-Dec-2023 $14,834.00 $13,277.65
Pump Station 065 Wet Well Rehabilitation EAST COAST INFRASTRUCTURE INC 21-Jun-2024 30-Dec-2024 $764,439.99 $764,439.99

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.