Project Description
Location: 521 Industrial Park DriveThe goal of the Jones Run Stormwater BMP Retrofit project is to retrofit the basin to address water quality to meet the City’s TMDL requirements per the MS4 permit. The basin will continue to provide flood control measures for large storm events while water quality functions will be added or improved. The accumulated sedimentation within the basin will be dredged.
Project Manager
Mohamed Khaye
(757)926-8649
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe
  • Respects its Uniqueness

Schedule

Activity Start Finish % Complete
PE/Design 19-Nov-2024 04-Sep-2027
52%
PE - Preliminary 19-Nov-2024 03-Nov-2025
100%
PE - Design 04-Nov-2025 04-Sep-2027
28%
PE - Environmental 02-Feb-2026 16-Apr-2027
22%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Construction 05-Sep-2027 21-Jul-2028
CA - Pre-Ad 05-Sep-2027 14-Sep-2027
CA - Advertisement 15-Sep-2027 04-Oct-2027
CA - Bid Date 05-Oct-2027 05-Oct-2027
CA - Construction Award 06-Oct-2027 04-Nov-2027
CA - CEI 05-Nov-2027 05-Nov-2027
CA - Construction 05-Nov-2027 22-May-2028
CA - Construction Closeout 23-May-2028 21-Jul-2028
Project Closeout 22-Jul-2028 19-Sep-2028
PE - Scoping 05-Nov-2018 05-Nov-2018
100%

Comments

Assuming there are no major changes to the SLAF program dates, below is the tentative timeline: September 2026 – We will apply for grant funding. January 2027 – We will hear if we have been awarded funding March 2027 – If we are awarded funding, this is likely when the project will begin. 11/21/2025

Eastern Virginia Tree Harvesters are expected to begin the tree clearing within this area between May to July of 2026. Mr. Nick Mrjoian, CF, Forester with Newport News Waterworks, is the City representative for this contract and is working closely with Eddie Harrah, CF, Chief of Natural Assets with Newport News Waterworks. 11/21/2025

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Jones Run SWMF Improvements Wetlands Studies and Solutions, Inc. 03-Dec-2024 01-Jan-2026 $67,770.98 $54,462.48
Jones Run Retrofit Design Arcadis-U.s., INC. 28-Jan-2026 30-Oct-2026 $328,281.00 $24,206.80

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.