Project Description
Bates Drive from 12 Street to King Lincoln Park.Bates Drive is currently a paper street that connects 12th Street to 6th Street. The project will improve the existing dilapidated sidewalk to a 10 foot wide multi use path that will serve to connect Ridley housing development to the King Lincoln Park.
Project Manager
Jennifer Butler
757.926.1582
butlerja@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 09-Sep-2021 31-Dec-2025
100%
PE - Preliminary / Consultant Selection 09-Sep-2021 31-May-2023
100%
PE - Design 01-Jun-2023 31-Dec-2025
100%
PE - Environmental / NEPA 14-Feb-2024 28-Nov-2025
100%
PE - Public Involvement 13-Sep-2024 12-Sep-2025
100%
Right of Way 01-Jan-2026 31-Dec-2026
36%
ROW - Land Acquisition 01-Jan-2026 31-Dec-2026
36%
ROW - Utility Relocation 01-Jan-2026 31-Dec-2026
36%
Construction 01-Jan-2027 26-Jan-2028
CA - Pre-Ad 01-Jan-2027 21-Jan-2027
CA - Advertisement 22-Jan-2027 24-Feb-2027
CA - Bid Date 25-Feb-2027 25-Feb-2027
CA - Construction Award 26-Feb-2027 26-Apr-2027
CA - CEI 27-Apr-2027 28-Oct-2027
CA - Construction 27-Apr-2027 28-Oct-2027
CA - Construction Closeout 29-Oct-2027 26-Jan-2028
Project Closeout 27-Jan-2028 25-May-2028
PE - PAA Execution 01-Sep-2022 01-Aug-2023
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Bates Drive Multi-Use Path GUERNSEY TINGLE ARCHITECTS, PC 15-Jun-2018 $44,784.00 $24,102.86
121111 Bates Dr MUP Design - JMT Johnson, Mirmiran & Thompson, Inc. 25-May-2023 07-Nov-2025 $407,602.69 $306,809.32

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.