Project Description
The 28th Street Garden Bridge would create new greenspace on the bridge itself and would also facilitate access to planned creative placemaking in Newport News such as the 28th and Washington Market Garden. The Garden Bridge in combination with other projects included in the Newport News Vision Plan would be incredible amenities for all, visitors and residents alike. This would be a major contributor to the renaissance of Newport News creating a thriving, inclusive, resilient community. It would help address past inequalities and would bring economic development and job opportunities to all for shared prosperity. As part of further and necessary studies of the 28th Street Garden Bridge, the city would also investigate additional connections and improvements for bicyclists and pedestrians throughout the area. Access to local and regional public transit facilities would also be considered. The 28th Street Garden Bridge will not stand alone but will be part of a larger connected infrastructure to be utilized by all.
Project Manager
Mahzad Bastaninejad
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 14-Nov-2024 15-Jun-2026
94%
PE - Preliminary 14-Nov-2024 14-Jun-2025
100%
PE - Design 15-Jun-2025 15-Jun-2026
90%
PE - Environmental 14-Nov-2024 14-Jun-2025
100%
PE - Public Involvement 14-Jun-2025 14-Dec-2025
100%
Right of Way 14-Jun-2025 13-Jun-2027
45%
ROW - Land Acquisition 14-Jun-2025 13-Jun-2026
91%
ROW - Utility Relocation 14-Jun-2025 13-Jun-2027
45%
Construction 16-Jun-2027 21-Jun-2027
CA - Pre-Ad 16-Jun-2027 16-Jun-2027
CA - Advertisement 17-Jun-2027 17-Jun-2027
CA - Bid Date 18-Jun-2027 18-Jun-2027
CA - Construction Award 19-Jun-2027 19-Jun-2027
CA - CEI 20-Jun-2027 20-Jun-2027
CA - Construction 20-Jun-2027 20-Jun-2027
CA - Construction Closeout 21-Jun-2027 21-Jun-2027
Project Closeout 22-Jun-2027 22-Jun-2027
PE - Scoping 14-Nov-2024 14-Jun-2025
100%

Comments

Agreement not executed by FHWA 03/04/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
ATCS Application Assistance ATCS, P.L.C 30-Aug-2022 15-Oct-2022 $55,145.59 $55,145.59
RCP-NAE Funding Application Assistance ATCS, P.L.C 10-Aug-2023 02-Oct-2023 $34,451.68 $34,451.68

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.