Project Description
Project Manager
Angela Rico
757-926-8690
braswelld@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe
  • Respects its Uniqueness
  • Balances Good Places & New Spaces

Schedule

Activity Start Finish % Complete
PE/Design 14-Sep-2022 31-Jul-2025
100%
PE - Preliminary 14-Sep-2022 27-Apr-2023
100%
PE - Design 28-Apr-2023 31-Jul-2025
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 28-Apr-2023 31-Oct-2024
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 10-Nov-2018 10-Nov-2018
100%
CA - Pre-Ad 06-Nov-2018 06-Nov-2018
100%
CA - Advertisement 07-Nov-2018 07-Nov-2018
100%
CA - Bid Date 08-Nov-2018 08-Nov-2018
100%
CA - Construction Award 09-Nov-2018 09-Nov-2018
100%
CA - CEI 10-Nov-2018 10-Nov-2018
100%
CA - Construction 10-Nov-2018 10-Nov-2018
100%
CA - Construction Closeout 11-Nov-2018 11-Nov-2018
100%
Project Closeout 27-Jun-2025 31-Jul-2025
100%
PE - Scoping 28-Apr-2023 18-Dec-2024
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
KHA CMAQ/RSTP/SS4A Grant Assistance KIMLEY-HORN AND ASSOCIATES, INC 15-Aug-2022 15-Sep-2022 $57,978.57 $57,978.57
PREPARATION OF A CITY-WIDE SAFETY ACTION PLAN KIMLEY-HORN AND ASSOCIATES, INC 28-Dec-2023 30-Sep-2024 $205,590.62 $205,590.62
Implementation Grant Application KIMLEY-HORN AND ASSOCIATES, INC 07-May-2026 $36,365.70 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.