Project Description
Reconstruct the westerly side of Warwick Boulevard, between Rivedrmont Drive and Randolph Road. Improvements include sidewalk, curb and gutter, on-street parking , and ADA improvements, and appropriate lighting.
Project Manager
Melaney Hollins
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2027 01-Jul-2028
PE - Preliminary 01-Jul-2027 28-Sep-2027
PE - Design 29-Sep-2027 01-Jul-2028
PE - Environmental 29-Sep-2027 01-Jul-2028
Right of Way 02-Jul-2028 02-Jul-2029
ROW - Land Acquisition 02-Jul-2028 02-Jul-2029
ROW - Utility Relocation 02-Jul-2028 02-Jul-2029
Construction 03-Jul-2029 01-Jul-2030
CA - Pre-Ad 03-Jul-2029 01-Aug-2029
CA - Advertisement 02-Aug-2029 22-Aug-2029
CA - Bid Date 23-Aug-2029 23-Aug-2029
CA - Construction Award 24-Aug-2029 22-Sep-2029
CA - CEI 23-Sep-2029 01-Jun-2030
CA - Construction 23-Sep-2029 01-Jun-2030
CA - Construction Closeout 02-Jun-2030 01-Jul-2030
Project Closeout 02-Jul-2030 30-Aug-2030
PE - Scoping 29-Sep-2027 01-Jul-2028

Comments

Design expected to start Summer of 2027. 06/04/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.