Project Description
Sidewalk, HC ramps, crosswalks, and lighting along River Rd from Mercury Blvd/Huntington Park to 75th St.Intersection improvements at Mercury Blvd to include but not be limited to correcting the turning radii on theSE corner and refuge island.
Project Manager
Walter Johnson
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2026 30-Jun-2027
10%
PE - Preliminary 01-Jul-2026 28-Sep-2026
41%
PE - Design 29-Sep-2026 30-Jun-2027
PE - Environmental 29-Sep-2026 30-Jun-2027
Right of Way 01-Jul-2027 30-Jun-2028
ROW - Land Acquisition 01-Jul-2027 30-Jun-2028
ROW - Utility Relocation 01-Jul-2027 30-Jun-2028
Construction 01-Jul-2028 01-Jul-2029
CA - Pre-Ad 01-Jul-2028 30-Jul-2028
CA - Advertisement 31-Jul-2028 20-Aug-2028
CA - Bid Date 21-Aug-2028 21-Aug-2028
CA - Construction Award 22-Aug-2028 20-Sep-2028
CA - CEI 21-Sep-2028 01-Jun-2029
CA - Construction 21-Sep-2028 01-Jun-2029
CA - Construction Closeout 02-Jun-2029 01-Jul-2029
Project Closeout 02-Jul-2029 30-Aug-2029
PE - Scoping 29-Sep-2026 30-Jun-2027

Comments

Consultant selection has began. 07/10/2026

PE Phase opened 7/7/206. 07/07/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.