Project Description
Project Manager
Walter Johnson
hollinsmn@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2026 30-Jun-2027
10%
PE - Preliminary 01-Jul-2026 28-Sep-2026
41%
PE - Design 29-Sep-2026 30-Jun-2027
PE - Environmental 29-Sep-2026 30-Jun-2027
Right of Way 01-Jul-2027 02-Jul-2028
ROW - Land Acquisition 01-Jul-2027 02-Jul-2028
ROW - Utility Relocation 01-Jul-2027 02-Jul-2028
Construction 03-Jul-2028 02-Jul-2029
CA - Pre-Ad 03-Jul-2028 01-Aug-2028
CA - Advertisement 02-Aug-2028 22-Aug-2028
CA - Bid Date 23-Aug-2028 23-Aug-2028
CA - Construction Award 24-Aug-2028 22-Sep-2028
CA - CEI 23-Sep-2028 02-Jun-2029
CA - Construction 23-Sep-2028 02-Jun-2029
CA - Construction Closeout 03-Jun-2029 02-Jul-2029
Project Closeout 03-Jul-2029 31-Aug-2029
PE - Scoping 29-Sep-2026 30-Jun-2027

Comments

Consultant Selection has begun. 07/10/2026

PE Phase opened 7/7/2026 07/07/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.