Project Description
Project Manager
Jennifer Butler
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2026 30-Jun-2027
PE - Preliminary 01-Jul-2026 28-Sep-2026
PE - Design 29-Sep-2026 30-Jun-2027
PE - Environmental 29-Sep-2026 30-Jun-2027
Right of Way 01-Jul-2027 30-Jun-2028
ROW - Land Acquisition 01-Jul-2027 30-Jun-2028
ROW - Utility Relocation 01-Jul-2027 30-Jun-2028
Construction 01-Jul-2028 30-Jun-2029
CA - Pre-Ad 01-Jul-2028 30-Jul-2028
CA - Advertisement 31-Jul-2028 20-Aug-2028
CA - Bid Date 21-Aug-2028 21-Aug-2028
CA - Construction Award 22-Aug-2028 20-Sep-2028
CA - CEI 21-Sep-2028 31-May-2029
CA - Construction 21-Sep-2028 31-May-2029
CA - Construction Closeout 01-Jun-2029 30-Jun-2029
Project Closeout 01-Jul-2029 29-Aug-2029
PE - Scoping 29-Sep-2026 30-Jun-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.