Project Description
Project Manager
Melaney Hollins
Inspector
How does this project serve Newport News’ citizens?
Relationship to Comprehensive Plan Themes
Schedule
| Activity |
Start |
Finish |
% Complete |
| PE/Design |
01-Jul-2026 |
25-Aug-2028 |
|
| PE - Preliminary |
01-Jul-2026 |
28-Sep-2026 |
|
| PE - Design |
29-Sep-2026 |
25-Aug-2028 |
|
| PE - Environmental |
29-Sep-2026 |
30-Jun-2027 |
|
| Right of Way |
26-Aug-2028 |
26-Apr-2029 |
|
| ROW - Land Acquisition |
26-Aug-2028 |
26-Apr-2029 |
|
| ROW - Utility Relocation |
26-Aug-2028 |
26-Apr-2029 |
|
| Construction |
01-Mar-2028 |
01-Mar-2029 |
|
| CA - Pre-Ad |
01-Mar-2028 |
30-Mar-2028 |
|
| CA - Advertisement |
31-Mar-2028 |
20-Apr-2028 |
|
| CA - Bid Date |
21-Apr-2028 |
21-Apr-2028 |
|
| CA - Construction Award |
22-Apr-2028 |
21-May-2028 |
|
| CA - CEI |
22-May-2028 |
30-Jan-2029 |
|
| CA - Construction |
22-May-2028 |
30-Jan-2029 |
|
| CA - Construction Closeout |
31-Jan-2029 |
01-Mar-2029 |
|
| Project Closeout |
02-Mar-2029 |
30-Apr-2029 |
|
| PE - Scoping |
29-Sep-2026 |
30-Jun-2027 |
|
Contracts
| Contract Name |
Contractor/Consultant |
Start |
Finish |
Contract Amount |
Paid To Date |
| Traffic Signal Mast Arm for Brook at Jefferson Ave & Crittenden at Jefferson Ave Intersections |
KIMLEY-HORN AND ASSOCIATES, INC |
02-Dec-2025 |
01-Mar-2027 |
$226,303.93 |
$0.00 |
The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.