Schedule

Activity Start Finish % Complete
PE/Design 01-Jul-2026 25-Aug-2028
PE - Preliminary 01-Jul-2026 28-Sep-2026
PE - Design 29-Sep-2026 25-Aug-2028
PE - Environmental 29-Sep-2026 30-Jun-2027
Right of Way 26-Aug-2028 26-Apr-2029
ROW - Land Acquisition 26-Aug-2028 26-Apr-2029
ROW - Utility Relocation 26-Aug-2028 26-Apr-2029
Construction 01-Mar-2028 01-Mar-2029
CA - Pre-Ad 01-Mar-2028 30-Mar-2028
CA - Advertisement 31-Mar-2028 20-Apr-2028
CA - Bid Date 21-Apr-2028 21-Apr-2028
CA - Construction Award 22-Apr-2028 21-May-2028
CA - CEI 22-May-2028 30-Jan-2029
CA - Construction 22-May-2028 30-Jan-2029
CA - Construction Closeout 31-Jan-2029 01-Mar-2029
Project Closeout 02-Mar-2029 30-Apr-2029
PE - Scoping 29-Sep-2026 30-Jun-2027

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Traffic Signal Mast Arm for Brook at Jefferson Ave & Crittenden at Jefferson Ave Intersections KIMLEY-HORN AND ASSOCIATES, INC 02-Dec-2025 01-Mar-2027 $226,303.93 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.