Project Description
Location: Washington Ave from 28th to 25th St, 25th St from West Ave to Huntington Ave
Project Manager
Melaney Hollins
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 01-May-2024 15-Apr-2026
100%
PE - Preliminary 01-May-2024 26-Feb-2025
100%
PE - Design 27-Feb-2025 15-Apr-2026
100%
PE - Environmental 27-Feb-2025 15-Apr-2026
100%
PE - Public Involvement 27-Feb-2025 27-Feb-2026
100%
Right of Way 16-Apr-2026 14-Mar-2027
18%
ROW - Land Acquisition 16-Apr-2026 14-Mar-2027
18%
ROW - Utility Relocation 16-Apr-2026 14-Mar-2027
18%
Construction 15-Mar-2027 14-Mar-2028
CA - Pre-Ad 15-Mar-2027 13-Apr-2027
CA - Advertisement 14-Apr-2027 04-May-2027
CA - Bid Date 05-May-2027 05-May-2027
CA - Construction Award 06-May-2027 04-Jun-2027
CA - CEI 05-Jun-2027 13-Feb-2028
CA - Construction 05-Jun-2027 13-Feb-2028
CA - Construction Closeout 14-Feb-2028 14-Mar-2028
Project Closeout 15-Mar-2028 15-Mar-2028
PE - Scoping 27-Feb-2025 15-Apr-2026
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Design and CEI Services for UPC 121105 Washington Ave & 25th St SUP Volkert, Inc. 26-Feb-2025 01-Sep-2027 $608,423.15 $381,264.60

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.