Project Description
The project scope includes the maintenance dredging of the North End of the Inner Harbor of Seafood Industrial Park and demolition of the two existing timber piers prior to the dredge.  Dredging will preserve all existing infrastructure including the cylinder pile bulkheads and stone revetment along the north bulkhead. Maintenance dredging is required to restore berth depth.This project also includes construction of a new fixed pier system to support the commercial seafood fleet as well as a floating dock and piers to provide temporary public boat access to the upcoming Seafood Market.
Project Manager
Carolyn Bowman
757.926.3667
bowmancd@nnva.gov
Inspector
Jeff Everton
757.592.2123
evertonjw@nnva.gov

How does this project serve Newport News’ citizens?
This project will support the Economic Development and Redevelopment of the Seafood Industrial Park

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe
  • Respects its Uniqueness
  • Balances Good Places & New Spaces

Schedule

Activity Start Finish % Complete
PE/Design 01-Aug-2021 09-Jun-2025
100%
PE - Preliminary 01-Aug-2021 22-Mar-2023
100%
PE - Design 23-Mar-2023 09-Jun-2025
100%
PE - Environmental 23-Mar-2023 03-Sep-2024
100%
Construction 10-Jun-2025 30-May-2027
42%
CA - Pre-Ad 10-Jun-2025 26-Jun-2025
100%
CA - Advertisement 27-Jun-2025 07-Aug-2025
100%
CA - Bid Date 08-Aug-2025 08-Aug-2025
100%
CA - Construction Award 09-Aug-2025 30-Nov-2025
100%
CA - CEI 01-Dec-2025 01-Mar-2027
28%
CA - Construction 01-Dec-2025 01-Mar-2027
28%
CA - Construction Closeout 02-Mar-2027 30-May-2027
Project Closeout 31-May-2027 29-Jul-2027
Hold for Dredging 04-Sep-2024 02-Nov-2024
100%

Comments

Constractor is moving rip rap adjacent to the bulkhead to prepare for H-pile pile driving. H-piles have been delivered to the jobsite. 03/23/2026

Dredging is complete. Contractor is verifying through a post-dredge survey. 03/17/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Seafood Industrial Park - Pier and Dock at North End of Inner Harbor MOFFATT AND NICHOL 23-Mar-2023 30-Apr-2027 $501,955.00 $2,522,070.44
Seafood Industrial Park Inner Harbor Dredging, Pier and Dock - North End CROFTON CONSTRUCTION SERVICES, INC 01-Dec-2025 01-Dec-2026 $7,212,635.00 $2,522,070.44
NXL - Inspection Services CENTURY ENGINEERING, INC 02-Mar-2026 31-Mar-2027 $190,427.43 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.