Project Description
This is at the intersection of Jefferson Avenue and Wilcox Lane. We will be doing a little bit of asphalt work on the approaches on Jefferson Avenue just for purposes of adjusting the grade for ADA compliance.
Project Manager
Randy Cooper
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 01-Feb-2023 25-May-2024
100%
PE - Preliminary 01-Feb-2023 01-May-2023
100%
PE - Design 02-May-2023 31-Jan-2024
100%
PE - Environmental 02-May-2023 31-Jan-2024
100%
PE - Public Involvement 01-Jun-2023 25-May-2024
100%
Right of Way 01-Jul-2025 30-Jun-2026
100%
ROW - Land Acquisition 01-Jul-2025 30-Jun-2026
100%
ROW - Utility Relocation 01-Jul-2025 30-Jun-2026
100%
Construction 24-Feb-2027 24-Feb-2028
CA - Pre-Ad 24-Feb-2027 25-Mar-2027
CA - Advertisement 26-Mar-2027 15-Apr-2027
CA - Bid Date 16-Apr-2027 16-Apr-2027
CA - Construction Award 17-Apr-2027 16-May-2027
CA - CEI 17-May-2027 25-Jan-2028
CA - Construction 17-May-2027 25-Jan-2028
CA - Construction Closeout 26-Jan-2028 24-Feb-2028
Project Closeout 25-Feb-2028 25-Feb-2028
PE - Scoping 02-May-2023 31-Jan-2024
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
DESIGN FOR TRAFFIC SIGNAL TO MAST ARM CONVERSION AT JEFFERSON AND WILCOX - UPC 117135 MCPHERSON CONSULTING, LLC 06-Sep-2023 15-Dec-2024 $58,160.46 $40,108.41

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.