Project Description
Project Manager
Jennifer Butler
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 02-Sep-2025 27-Jul-2027
41%
PE - Preliminary 02-Sep-2025 02-Sep-2025
100%
PE - Design 03-Sep-2025 24-Jul-2027
41%
PE - Environmental 25-Jul-2027 25-Jul-2027
PE - Public Involvement 27-Jul-2027 27-Jul-2027
Construction 28-Jul-2027 11-Dec-2028
CA - Pre-Ad 28-Jul-2027 28-Jul-2027
CA - Advertisement 29-Jul-2027 29-Jul-2027
CA - Bid Date 30-Jul-2027 30-Jul-2027
CA - Construction Award 31-Jul-2027 31-Jul-2027
CA - CEI 01-Aug-2027 01-Aug-2027
CA - Construction 01-Aug-2027 10-Dec-2028
CA - Construction Closeout 11-Dec-2028 11-Dec-2028
Project Closeout 12-Dec-2028 12-Dec-2028
PE - Scoping 26-Jul-2027 26-Jul-2027

Comments

$100k in FY25 & $400k in FY26 10/25/2022

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.