This funding will allow for the review of traffic signal coordination, phasing and other timing settings accross the City.  This is a Citywide project. Specific intersections will be determined based on available funding and current requests from citizens and changes of traffic flow in areas of the City.
Project Manager
Randy Cooper
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 02-Nov-2024 03-Nov-2027
58%
PE - Preliminary 02-Nov-2024 02-Nov-2024
100%
PE - Design 03-Nov-2024 03-Nov-2027
58%
PE - Environmental 05-Nov-2024 05-Nov-2025
100%
PE - Public Involvement 05-Nov-2024 05-Nov-2024
100%
Construction 09-Nov-2027 09-Nov-2027
CA - Pre-Ad 04-Nov-2027 04-Nov-2027
CA - Advertisement 05-Nov-2027 05-Nov-2027
CA - Bid Date 06-Nov-2027 06-Nov-2027
CA - Construction Award 07-Nov-2027 07-Nov-2027
CA - CEI 08-Nov-2027 08-Nov-2027
CA - Construction 08-Nov-2027 08-Nov-2027
CA - Construction Closeout 09-Nov-2027 09-Nov-2027
Project Closeout 10-Nov-2027 10-Nov-2027
PE - Scoping 05-Nov-2024 31-Jan-2025
100%

Comments

Purchase Order 20270936 was issued to Kimley-Horn and Associates, INC in the amount of $1,121,046.00. This project is expected to last about two years. This project is a study and implementation only project and has no construction. 07/29/2026

VDOT offered and City concurred to have VDOT perform the NEPA documentation which should meet the standards for OTPCE 05/19/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Retiming Project KIMLEY-HORN AND ASSOCIATES, INC $0.00 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.