Project Description
Citywide Bicycle & Pedestrian Master Plan
Project Manager
Angela Rico
Inspector
How does this project serve Newport News’ citizens?
Relationship to Comprehensive Plan Themes
Schedule
| Activity |
Start |
Finish |
% Complete |
| PE/Design |
01-Jan-2022 |
30-Dec-2022 |
|
| PE - Preliminary |
01-Jan-2022 |
01-Jan-2022 |
|
| PE - Design |
02-Jan-2022 |
01-Dec-2022 |
|
| PE - Environmental |
30-Dec-2022 |
30-Dec-2022 |
|
| PE - Public Involvement |
02-Jan-2022 |
02-Jan-2022 |
|
| Project Closeout |
01-Jan-2023 |
28-Feb-2023 |
|
| PE - Scoping |
02-Jan-2022 |
02-Jan-2022 |
|
Contracts
| Contract Name |
Contractor/Consultant |
Start |
Finish |
Contract Amount |
Paid To Date |
| Professional Services Citywide Bicycle and Pedestrian Master Plan |
Alta Planning and Design Inc |
24-Feb-2022 |
24-Nov-2022 |
$199,998.00 |
$176,593.50 |
| BIKE/PED MASTERPLAN PRIORITY PROJECT TRAFFIC STUDIES. |
KIMLEY-HORN AND ASSOCIATES, INC |
10-Jul-2025 |
25-Aug-2026 |
$248,197.62 |
$151,758.16 |
The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.