Project Description
Pump Station 19 must be evaluated for capacity and to correct deficiencies discovered recently to bring it up to a normal working condition to pump the flow to match the capabilities of the force main. Several items at each pump station need attention – bypass pumping or generators, wet well rehabilitation, pump capacity and performance issues, roof replacement or rehabilitation, general structural repair, SCADA upgrade, and electrical controls upgrade. A consulting firm has been selected to conduct a Preliminary Engineering Study to provide a comprehensive improvement plan with a cost effective solution, followed by design.Location: 620 HARPERSVILLE RD
Project Manager
Landon Kee
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 15-Apr-2022 14-Nov-2025
100%
PE - PER phase 15-Apr-2022 19-Jan-2023
100%
PE - Design 21-Apr-2023 14-Nov-2025
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 15-Nov-2025 27-Nov-2027
19%
CA - Pre-Ad 15-Nov-2025 19-Jan-2026
100%
CA - Advertisement 20-Jan-2026 02-Mar-2026
100%
CA - Bid Date 03-Mar-2026 03-Mar-2026
100%
CA - Construction Award 04-Mar-2026 19-Mar-2026
100%
CA - CEI 20-Mar-2026 26-Mar-2026
100%
CA - Construction 27-Apr-2026 28-Oct-2027
CA - Construction Closeout 29-Oct-2027 27-Nov-2027
Project Closeout 28-Nov-2027 28-Nov-2027
PE - Scoping 05-Nov-2018 05-Nov-2018
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Preliminary Engineering Report (Pump Station 019) BURGESS & NIPLE, INC 15-Apr-2022 16-Jul-2022 $105,354.00 $105,354.00
Professional Design Services: Pump Station 019 Replacement BURGESS & NIPLE, INC 21-Apr-2023 31-Jan-2024 $402,679.79 $324,806.21
Verizon Utility Relocation (Pump Station 019) VERIZON 15-Dec-2025 31-May-2026 $51,966.81 $0.00
Pump Station 019 Replacement SHAW Construction Corporation 27-Apr-2026 28-Oct-2027 $3,410,000.00 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.