Project Description
The City determined that Pump Station 54 should be replaced rather than repaired. Therefore, a consulting firm has been selected to conduct a Preliminary Engineering Study, which will serve as the basis of design for pump station replacement. Location: 91 Linda Drive
Project Manager
Landon Kee
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 15-Apr-2022 07-Oct-2024
100%
PE - PER phase 15-Apr-2022 01-Dec-2022
100%
PE - Design 21-Apr-2023 07-Oct-2024
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 08-Oct-2024 18-Jan-2027
77%
CA - Pre-Ad 08-Oct-2024 05-Jan-2025
100%
CA - Advertisement 06-Jan-2025 03-Feb-2025
100%
CA - Bid Date 04-Feb-2025 04-Feb-2025
100%
CA - Construction Award 05-Feb-2025 14-Mar-2025
100%
CA - CEI 15-Mar-2025 23-Apr-2025
100%
CA - Construction 24-Apr-2025 19-Dec-2026
73%
CA - Construction Closeout 20-Dec-2026 18-Jan-2027
Project Closeout 19-Jan-2027 19-Jan-2027
PE - Scoping 05-Nov-2018 05-Nov-2018
100%

Comments

WACO was on site today with A+ Concrete. Contractor was pouring the slab/floor for the wet well today. Temp were around 40 degrees at the time of pour. Contractor informed to cover the concrete when they had finished brooming it this afternoon. Terracon was on site today for concrete testing. Tests were found to be acceptable for pour. Air- 7.2% Slump- 7.25 6 cylinders made Substantial completion: December 3rd, 2027 12/10/2025

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Preliminary Engineering Report - (Pump Station 054) BURGESS & NIPLE, INC 15-Apr-2022 16-Jul-2022 $56,525.00 $56,525.00
Professional Design Services: Pump Station 054 Replacement BURGESS & NIPLE, INC 21-Apr-2023 31-Jan-2024 $290,276.45 $252,203.18
Pump Station 054 Replacement WACO INC 24-Apr-2025 20-Sep-2026 $2,249,042.65 $1,247,599.09

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.