Project Description
BMP will be designed to handle the flow from Municipal lane and the library and will be a basin for water flowing to the Main Street Underpass Pump Station.
Project Manager
Marcus Clements
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 05-Nov-2018 31-Aug-2023
100%
PE - Preliminary 03-Jan-2022 02-Mar-2022
100%
PE - Design 03-Mar-2022 31-Aug-2023
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 05-Nov-2018 05-Nov-2018
100%
ROW - Land Acquisition 05-Nov-2018 05-Nov-2018
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 30-Oct-2023 15-Nov-2024
100%
CA - Pre-Ad 30-Oct-2023 09-Nov-2023
100%
CA - Advertisement 10-Nov-2023 29-Nov-2023
100%
CA - Bid Date 30-Nov-2023 30-Nov-2023
100%
CA - Construction Award 01-Dec-2023 04-Jan-2024
100%
CA - CEI 05-Jan-2024 05-Jan-2024
100%
CA - Construction 12-Jan-2024 14-Oct-2024
100%
CA - Construction Closeout 15-Oct-2024 15-Nov-2024
100%
Project Closeout 16-Nov-2024 24-Jan-2025
100%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Main Street BMP CORNWELL ENGINEERING GROUP 13-Mar-2020 21-Aug-2020 $281,700.00 $120,466.87
Main Street BMP BASIC CONSTRUCTION CO.,L.L.C 12-Dec-2023 14-Oct-2024 $1,537,020.78 $1,510,936.78

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.