Project Description
The Pearl Bailey Library, Doris Miller Community Center, and community program space will be combined into a single, collaborative community resource that provides access to all community uses and engages the historic core of the original Huntington School as a shared community resource for the neighborhood and the greater Newport News community. The original building will be retained and repurposed to include meeting and multi-purpose activity spaces. the new community building includes indoor pool facility for year-round community use, the New Peral Bailey library, and outdoor green spaces.
Project Manager
Bruce Wobser
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 04-Mar-2022 16-Jun-2023
100%
PE - Preliminary 04-Mar-2022 16-Jun-2023
100%
PE - Design 04-Mar-2022 15-Jun-2023
100%
PE - Environmental 16-Jun-2023 16-Jun-2023
100%
PE - Public Involvement 16-Jun-2023 16-Jun-2023
100%
Right of Way 04-Mar-2022 15-Jun-2023
100%
ROW - Land Acquisition 04-Mar-2022 15-Jun-2023
100%
ROW - Utility Relocation 04-Mar-2022 15-Jun-2023
100%
Construction 09-Jan-2024 14-Sep-2026
99%
CA - Pre-Ad 09-Jan-2024 29-Feb-2024
100%
CA - Advertisement 01-Mar-2024 04-Apr-2024
100%
CA - Bid Date 12-Apr-2024 12-Apr-2024
100%
CA - Construction Award 13-Apr-2024 09-May-2024
100%
CA - CEI 03-May-2024 03-May-2024
100%
CA - Construction 03-May-2024 15-Aug-2026
100%
CA - Construction Closeout 16-Aug-2026 14-Sep-2026
86%
Project Closeout 09-Jun-2026 07-Aug-2026
100%
PE - Scoping 16-Jun-2023 16-Jun-2023
100%

Comments

Substantial Completion -8-15-2026 Final Completion - 9-15-2026 Change Order % - 2.08% Roof deck is being installed, mechanical pumps and water heaters installed, duct work has started, Steel still not complete. Contractor is still having issues with the structural steel non-conforming, issues with the safety of the work are now a concern. Contractor continues to install work over non-conforming or work that needs to be inspected, requiring tear out of installed work. Add. non-conforming issues: dry wall, insulation being installed without building being dried in, mechanical units being stored in a non-dryin building, ceiling tiles and grid. Haz mtls and LEED inspections started. City waiting on the MEB schedule with dry-in and electrical start up dates, this has been requested since April. 08/19/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
SECRA Miller Center Design and Constrcution QUINN EVANS ARCHITECTS, INC 24-Mar-2022 30-Sep-2023 $4,638,052.00 $4,081,113.40
SECRA - Huntington Community Center MEB GENERAL CONTRACTORS, INC 03-Jun-2024 05-Mar-2026 $54,460,433.41 $31,185,910.08
SECRA - Huntington Community Center ESCROW MEB GENERAL CONTRACTORS, INC 03-Jun-2024 05-Mar-2026 $2,723,021.68 $1,641,363.69
Recreation Center- MCDONOUGH BOLYARD PECK, INC. Newport News - Engineering 21-Feb-2025 30-Jun-2025 $12,144.00 $11,319.00
Asbestos Abatement WACO INC 17-Apr-2025 17-Apr-2025 $219,495.00 $219,495.00
SECRA HUNTINGTON REC CENTER MCDONOUGH BOLYARD PECK, INC (MBP) 12-Feb-2026 31-Dec-2026 $30,322.24 $13,703.32
SECRA HUNTINGTON REC CENTER MCDONOUGH BOLYARD PECK, INC (MBP) 18-Feb-2026 27-Dec-2026 $2,915.60 $0.00

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.