Project Description
The project proposes the upgrade of the existing stairs and non-compliant ramps with the purpose of bringing existing pedestrian access up to the current ADA / VDOT Standards along Marshall Avenue, at the intersections with 20th Street, 21st Street, Hampton Ave., 22nd Street, and 23rd Street. The proposed upgrades are intended to increase pedestrian, and disabled accessibility.
Project Manager
Ioana Verde
(757) 926-8314
verdeic@nnva.gov
Inspector

(757) 933-2318
murdaughhm@nnva.gov

How does this project serve Newport News’ citizens?
Will improve and create safe pedestrian and disabled accessibility.

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe
  • Respects its Uniqueness
  • Balances Good Places & New Spaces

Schedule

Activity Start Finish % Complete
PE/Design 12-Oct-2022 28-Feb-2025
100%
PE - Consultant Selection 12-Oct-2022 17-Jan-2023
100%
PE - Design 18-Jan-2023 28-Feb-2025
100%
PE - Public Involvement 06-Aug-2023 06-Sep-2023
100%
Right of Way 14-Nov-2024 17-Mar-2025
100%
ROW - Utility Relocation 14-Nov-2024 17-Mar-2025
100%
Construction 18-Mar-2025 04-Aug-2026
90%
CA - Pre-Ad 18-Mar-2025 29-Apr-2025
100%
CA - Advertisement 30-Apr-2025 29-May-2025
100%
CA - Bid Date 30-May-2025 30-May-2025
100%
CA - Construction Award 31-May-2025 17-Nov-2025
100%
CA - CEI 18-Nov-2025 01-Jun-2026
100%
CA - Construction 23-Feb-2026 05-Jun-2026
100%
CA - Construction Closeout 06-Jun-2026 04-Aug-2026
16%
Project Closeout 05-Aug-2026 02-Dec-2026

Comments

Construction complete. Project acceptance on May 20th, 2026. 05/20/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Marshall Ave ADA Improvements - Design - RDA RINKER DESIGN ASSOCIATES, P.C. 14-Dec-2022 30-Nov-2024 $222,866.00 $222,866.00
Marshall Ave & 20th St - ADA Improvements FINLEY ASPHALT AND SEALING, LLC 23-Feb-2026 23-Jun-2026 $229,267.15 $199,267.15

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.