Project Description
The Department of Conservation and Recreation (DCR) notified the City that they believe the earth impounding structure for Sluice Mill Pond should be a regulated dam. The structure has been preliminarily evaluated and it appears the structure could qualify as a regulated dam. A formal evaluation will be performed to determine the hazard category and accompanying requirements. Warwick Blvd and a sanitary pump station are just downstream of the dam and consideration must be made for protecting the road during a dam failure. The hazard classification for the dam will determine the required storm the dam must safely pass.
Project Manager
Juan Carlos Morgado
(757)926-8655
anglekk@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 01-Nov-2021 18-Jan-2028
71%
PE - Preliminary 01-Nov-2021 22-Jan-2024
100%
PE - Design 23-Jan-2024 18-Jan-2028
55%
PE - Environmental 21-Jul-2024 05-Jul-2025
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 10-Aug-2024 25-Feb-2025
100%
ROW - Land Acquisition 10-Aug-2024 25-Feb-2025
100%
ROW - Utility Relocation 05-Nov-2018 05-Nov-2018
100%
Construction 19-Jan-2028 09-Mar-2030
CA - Pre-Ad 19-Jan-2028 28-Jan-2028
CA - Advertisement 29-Jan-2028 27-Feb-2028
CA - Bid Date 28-Feb-2028 28-Feb-2028
CA - Construction Award 29-Feb-2028 27-Jun-2028
CA - CEI 28-Jun-2028 09-Nov-2029
CA - Construction 28-Jun-2028 09-Nov-2029
CA - Construction Closeout 10-Nov-2029 09-Mar-2030
Project Closeout 10-Mar-2030 07-Jun-2030
PE - Scoping 05-Nov-2018 05-Nov-2018
100%

Comments

The City has hired Arcadis, through our annual services contract to perform the preliminary evaluation of the dam. The preliminary evaluation will determine if the dam is regulated and the hazard classification. Arcadis will also prepare grant applications for several of the required initial tasks. 11/10/2021

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Sluice Mill Dam Improvements Preliminary Design Arcadis-U.s., INC. 28-Mar-2022 28-Apr-2023 $283,489.23 $283,489.23
Sluice Mill Dam Inspection (Years 2025 and 2026) Arcadis-U.s., INC. 15-May-2025 30-Jun-2026 $40,866.08 $14,609.94
Sluice Mill Dam Safety Improvements Arcadis-U.s., INC. 22-Sep-2025 30-Dec-2026 $142,074.00 $120,584.46

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.