Project Description
Hampton Roads Express Lanes Segment 4A & 4B (from LaSalle Ave to Jefferson Ave)
Project Manager
Angela Rico
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes

Schedule

Activity Start Finish % Complete
PE/Design 22-Sep-2020 31-Oct-2023
100%
PE - Preliminary 22-Sep-2020 11-May-2021
100%
PE - Design 12-May-2021 28-Oct-2023
100%
PE - Environmental 29-Oct-2023 29-Oct-2023
100%
PE - Public Involvement 31-Oct-2023 31-Oct-2023
100%
Right of Way 01-Nov-2023 02-Nov-2023
100%
ROW - Land Acquisition 01-Nov-2023 01-Nov-2023
100%
ROW - Utility Relocation 02-Nov-2023 02-Nov-2023
100%
Construction 03-Nov-2023 09-Nov-2023
100%
CA - Pre-Ad 03-Nov-2023 03-Nov-2023
100%
CA - Advertisement 04-Nov-2023 04-Nov-2023
100%
CA - Bid Date 05-Nov-2023 05-Nov-2023
100%
CA - Construction Award 06-Nov-2023 06-Nov-2023
100%
CA - CEI 07-Nov-2023 07-Nov-2023
100%
CA - Construction 08-Nov-2023 08-Nov-2023
100%
CA - Construction Closeout 09-Nov-2023 09-Nov-2023
100%
Project Closeout 10-Nov-2023 10-Nov-2023
100%
PE - Scoping 30-Oct-2023 30-Oct-2023
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.