Project Description
The work consists of lining various sizes of stormwater pipes with Cured-In-Place Pipe (CIPP) and Spray Lining, including bypass pumping, storm sewer cleaning, Closed Circuit Television (CCTV) inspection, and other related work at various locations where existing storm drain pipes are failing.
Project Manager
Khanh Khuu
757-926-8656
khuukx@nnva.gov
Inspector
Not yet assigned

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Prosperous & Resilient
  • Sustainable
  • Accessible
  • Healthy & Safe
  • Respects its Uniqueness
  • Balances Good Places & New Spaces

Schedule

Activity Start Finish % Complete
PE/Design 01-Jun-2021 09-Sep-2022
100%
PE - Preliminary 01-Jun-2021 30-Sep-2021
100%
PE - Design 01-Oct-2021 09-Sep-2022
100%
PE - Environmental 04-Oct-2021 04-Oct-2021
100%
PE - Public Involvement 06-Oct-2021 06-Oct-2021
100%
Right of Way 13-Sep-2021 20-Sep-2021
100%
ROW - Land Acquisition 13-Sep-2021 13-Sep-2021
100%
ROW - Utility Relocation 20-Sep-2021 20-Sep-2021
100%
Construction 10-Sep-2022 30-Apr-2024
100%
CA - Pre-Ad 10-Sep-2022 13-Sep-2022
100%
CA - Advertisement 14-Sep-2022 17-Oct-2022
100%
CA - Bid Date 18-Oct-2022 18-Oct-2022
100%
CA - Construction Award 19-Oct-2022 13-Dec-2022
100%
CA - CEI 14-Dec-2022 14-Dec-2022
100%
CA - Construction 30-Jan-2023 29-Jan-2024
100%
CA - Construction Closeout 30-Jan-2024 30-Apr-2024
100%
Project Closeout 01-May-2024 01-May-2024
100%
PE - Scoping 05-Oct-2021 05-Oct-2021
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
2022 Annual Citywide Pipe Lining (Rebid) TRI-STATE UTILITIES CO 23-Feb-2023 30-Jan-2024 $2,179,053.10 $735,619.71
Annual Citywide Pipe Lining Project, Group #1 TRI-STATE UTILITIES CO 23-Feb-2023 30-Jan-2024 $774,349.14 $735,619.71
Annual Citywide Pipe Lining Project, Group #2 TRI-STATE UTILITIES CO 01-May-2023 30-Jan-2024 $33,175.12 $33,175.12
Annual Citywide Pipe Lining Project, Group #3 Pipe Lining - 29 Cherbourg Drive TRI-STATE UTILITIES CO 01-Aug-2023 30-Jan-2024 $56,630.50 $56,630.50

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.