Project Description
Trail757(former Birthplace of America Trail) is a multi-use trail that will be the centerpiece of a regional active transportation plan to connect the Virginia Capital Trail with the South Hampton Roads Trail in Eastern Virginia.This project is planned for the area of NN Park & Yorktown Rd to Chelsea Place.
Project Manager
Mahzad Bastaninejad
757-926-8605
bastaninejadm@nnva.gov
Inspector

How does this project serve Newport News’ citizens?

Relationship to Comprehensive Plan Themes
  • Accessible
  • Healthy & Safe

Schedule

Activity Start Finish % Complete
PE/Design 08-Sep-2023 12-Feb-2026
100%
PE - Preliminary 08-Sep-2023 21-Oct-2024
100%
PE - Design 21-Oct-2024 12-Feb-2026
100%
PE - Environmental 21-Oct-2024 17-Feb-2025
100%
Right of Way 13-Feb-2026 13-Feb-2027
15%
ROW - Land Acquisition 13-Feb-2026 13-Feb-2027
15%
ROW - Utility Relocation 13-Feb-2026 13-Feb-2027
15%
Construction 14-Feb-2027 27-Apr-2029
CA - Pre-Ad 14-Feb-2027 14-May-2027
CA - Advertisement 15-May-2027 13-Jun-2027
CA - Bid Date 14-Jun-2027 12-Aug-2027
CA - Construction Award 13-Aug-2027 11-Sep-2027
CA - CEI 12-Sep-2027 27-Jan-2029
CA - Construction 12-Sep-2027 27-Jan-2029
CA - Construction Closeout 28-Jan-2029 27-Apr-2029
Project Closeout 28-Apr-2029 26-Jul-2029
PE - Scoping 08-Sep-2023 12-Feb-2026
100%

Comments

Scoping closed 03.04.2026. Awaiting DHR's approval or the PCE and move to RW phase. 03/04/2026

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Design Services for BoAT Projects Johnson, Mirmiran & Thompson, Inc. 19-Oct-2024 30-Sep-2025 $926,219.33 $633,330.42

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.