Schedule

Activity Start Finish % Complete
PE/Design 05-Aug-2021 05-Aug-2022
100%
PE - Preliminary 02-Nov-2018 02-Nov-2018
100%
PE - Design 05-Aug-2021 05-Aug-2022
100%
PE - Environmental 05-Nov-2018 05-Nov-2018
100%
PE - Public Involvement 05-Nov-2018 05-Nov-2018
100%
Right of Way 14-Oct-2022 14-Oct-2022
100%
ROW - Land Acquisition 14-Oct-2022 14-Oct-2022
100%
ROW - Utility Relocation 14-Oct-2022 14-Oct-2022
100%
Construction 17-Oct-2022 03-Feb-2025
100%
CA - Pre-Ad 17-Oct-2022 05-Dec-2022
100%
CA - Advertisement 06-Dec-2022 23-Jan-2023
100%
CA - Bid Date 24-Jan-2023 31-Jan-2023
100%
CA - Construction Award 01-Feb-2023 23-Feb-2023
100%
CA - CEI 21-Sep-2021 21-Sep-2021
100%
CA - Construction 24-Feb-2023 20-Dec-2024
100%
CA - Construction Closeout 21-Dec-2024 03-Feb-2025
100%
Project Closeout 04-Feb-2025 04-Apr-2025
100%
PE - Scoping 05-Nov-2018 05-Nov-2018
100%

Comments

Map

Contracts

Contract Name Contractor/Consultant Start Finish Contract Amount Paid To Date
Architectural Services QUINN EVANS ARCHITECTS, INC 05-Aug-2021 01-Nov-2023 $1,239,251.22 $1,235,152.15
Early Childhood Development Center M B KAHN CONSTRUCTION CO INC 20-Mar-2023 18-May-2024 $14,488,900.35 $14,488,900.35
Electric Service VIRGINIA ELECTRIC AND POWER COMPANY 25-Mar-2024 28-Mar-2024 $21,533.17 $21,533.17
Furniture Newport News - Engineering 12-Aug-2024 30-Nov-2024 $861,066.02 $860,753.02

The data contained on this page is for general information purposes only. While endeavoring to keep the information up to date and correct, the City of Newport News disclaims any responsibility for the accuracy of the data. Please verify with the project manager before making any decisions or taking any actions based on this information.